1320MW Coal Based Thermal Power Plant Project Including Clearing & Grabbing 400.00 Acre (approx.) and Filling Sand 7310132.52 Cum, Average HT of filling
4.10 m, Clearing 170641.76 cum under North West Power Generation Company Ltd.
Contract Value : BDT 3066.66 Million